The township's detour notice is written in all capitals: "NORTH BANK TRAIL CLOSED AHEAD PLEASE FOLLOW THE DETOUR!" Then come three turns. Go north on N. Fruitport Road, east on State Road, and south on 148th Avenue until you meet the trail again. The map covers only the stretch between North Fruitport Road and 148th Avenue. That is the piece of the old rail line that gave way in May, and Spring Lake Township says it will stay closed until spring 2027.
The map leaves something out. While the trail bed was being stabilized, the township was also building a new 8-foot-wide path on Hickory Street. It runs from Fruitport Road to 148th Avenue, the same two endpoints as the closed section. The trail's busiest corridor lost a link this year, and it may have gained a better one at the same time.
What gave way on May 10
A section of the North Bank Trail collapsed on May 10, 2026. The township still hasn't confirmed why. Its best working theory is that the land bridge under the trail sits on old timbers and other organic material, which probably rotted after years of soaking in water. The trail follows a former railroad line.
The collapse also damaged a sewer line under the trail. Experts from the health department and Michigan's Department of Environment, Great Lakes, and Energy told the township the pipe had probably not been leaking before. A leak would have left darkened soil around the pipe, and crews found none. That sewer line is why this repair is bigger than a pothole. The ground had to be stabilized and the pipe fixed before anyone could think about pavement.
The trees went too. Township Manager Gordon Gallagher said the collapse "unfortunately, meant the loss of a bunch of trees." Expect the reopened section to have less shade than the one people remember.
Why the asphalt waits for spring
The repair has three phases, and most of the heavy work happens this year. Northern Pipeline and Schmidt Bros. Excavating finished Phase 1, which stabilized the ground under the trail and made a temporary sewer repair. Phase 2 covers the permanent sewer replacement and slope stabilization. On July 13 the Board of Trustees voted unanimously to approve $391,500 for those first two phases.
Phase 3 is the trail itself, meaning paving and reconstruction. The Grand Haven Tribune reported that project engineer Prein & Newhof recommended holding off on asphalt paving until spring 2027. The township skipped bidding on the first two phases because the collapse was an emergency. Trustees want a more competitive process for Phase 3, so it will go out to bid. The Laker Anchor says the reconnection has to wait until the ground settles.
All three phases together come to roughly $700,000. The township's insurer, Michigan Township Participating Plan, has denied coverage, which leaves the bill with local taxpayers.
"This was a pretty significant disappointment. They said, 'We do not cover any underground facilities,' and that seems odd to me." Gordon Gallagher, Spring Lake Township manager, at the July 13 board meeting
Gallagher said the township is appealing the denial and may look for a new insurer.
The official detour, turn by turn
The township's posted detour sends trail users around the closed section on State Road.
Heading east toward 148th Avenue:
- Turn north onto N. Fruitport Road.
- Turn east onto State Road.
- Turn south onto 148th Avenue and rejoin the North Bank Trail.
Heading west toward N. Fruitport Road:
- Turn north onto 148th Avenue.
- Turn west onto State Road.
- Turn south onto N. Fruitport Road and rejoin the trail.
The map lists roads only. It doesn't say whether the route has sidewalks, shoulders, or a separate path, so ride or walk it the first time expecting to share space with traffic. The Laker Anchor reported that the closure has frustrated residents who use the path every day. A three-sided loop through road traffic is a real change for anyone who used to ride straight through on the old railbed.
Hickory Street covers the same stretch
The Hickory Street path wasn't built because of the collapse. It's part of a bike path expansion the township planned well before May. Trustees approved the project at an estimated $3.8 million, paid for by voter-approved millages. FOX 17 reported that it is funded by two 10-year millages voters passed in fall 2024, one to maintain existing trails and one to add new ones.
The new path happens to line up with the gap. The Tribune described it as an 8-foot-wide trail running from Fruitport Road to 148th Avenue, with about four weeks of construction, Monday through Friday, after a four-week delay from the contractor. The work included filling ditches, installing storm sewers, removing trees, and building driveway crossings. As of early October, we haven't seen a public completion announcement. If the schedule held, the path should be finished or close to it. Check it in person or with the township before you build a commute around it.
Here's how the rest of the expansion stands this fall:
| Segment | What it covers | Status as of early October 2026 |
|---|---|---|
| Phase 1, State Road | 148th Avenue to 144th Avenue | Open; ribbon cutting reported June 19, 2026 |
| Phase 1, 174th Avenue | About 1,300 feet north of Van Wagoner, east side | Open with the State Road section |
| Phase 2, Hickory Street | Fruitport Road to 148th Avenue | Built this year after a contractor delay; completion not yet announced |
| Phase 2, Rannes Street | Leonard Street to 152nd Avenue | Delayed to early September; six-week job forecast to wrap in mid-October |
| Phase 3, Boom Road | Segment still in community engagement | No start date published |
The State Road segment matters to anyone using the detour. The detour already sends eastbound riders onto State Road, and the new path picks up at 148th Avenue and heads east toward 144th. Supervisor Jerry Rabideau called it "an important connection piece," extending the bike path "a little bit more to our east," and said community members had "been waiting for a while for this particular path to go in on state roads." The township now has more than 25 miles of trails, and FOX 17 reported the full expansion is expected to be finished by summer 2027.
Put the timelines together. By the time the North Bank Trail section is repaved next spring, the area around it should have a parallel path on Hickory, a finished Rannes segment, and the State Road link east of 148th. The repair is due around spring and the expansion by summer 2027, so the network should come back larger than it was before May.
Fall miles away from the bike path
For a walk instead of a commute, several preserves near the closure are open this season. Fall brings some rules worth checking first.
- Mill Point Park, the Village park, has a walking and biking trail, a nature preserve, and a wetlands boardwalk.
- Rycenga Park, shared by Spring Lake and Fruitport townships, has nature trails and a connection to the community bike path. It's open dawn to dusk.
- Connor Bayou, an Ottawa County park, has hiking trails and boardwalks. Hours change on October 16, from 7 a.m. to 10 p.m. down to 7 a.m. to 8 p.m.
- Crockery Creek Natural Area has about two miles of hiking and cross-country ski trails, on the same October 16 hours change. The county allows archery and waterfowl hunting there by special permit.
- Bur Oak Landing allows off-trail hiking but has no designated trails. The county permits hunting in both its east and west sections, under different rules.
At Crockery Creek and Bur Oak Landing, check the county's hunting rules before an October walk and wear something bright. With the evening cutoff at the county parks moving earlier in mid-October, Mill Point Park is the easiest choice for an after-work loop.
If you need more trail time, the dune preserves just west in Ferrysburg are covered in our Ferrysburg outdoor playbook.
What to watch between now and spring
The next real signal is the Phase 3 bid award. The township has agreed to bid out the paving and reconstruction. In the township news and Tribune and MLive coverage we've seen through early October, no contractor has been named and no earlier reopening date has been set. A contract award on a board agenda will tell you more about spring timing than any general update.
The Village and Township also added tools in September that help here. Since September 14, residents can use SeeClickFix to report issues like potholes and broken streetlights to the Village or Township, and submissions are public. Since September 18, both offer optional urgent alerts by text, email, or phone for road closures, utility issues, and infrastructure projects. Signing up for those alerts is the most direct way to hear when the North Bank Trail section reopens or when another segment of the expansion opens.
At Sandi Gentry, we follow projects like the Hickory Street path because trail connections shape everyday life around Spring Lake, from the morning ride to the walk after dinner. If you'd like to know how the growing path network reaches your street, or how it might matter when you sell, take a look at our Spring Lake neighborhood guide or request a free home valuation and we'll walk you through it.